Tuesday they are supposed to start pouring cement. My shed is 60' x 80', 1/2 to be cemented (60 x 40) My ? is, do you put down plastic or not? No floor heat tubes. I have heard people swear both ways, yes and no...... So! This cement will be a hybrid shop. I may insulate 1/2 the shed and ceiling.(cement area) But only use a curtain to divide the cement area and the non-heated I only work a few days a week, in the winter in the shed, unless it is a major project. Since I have heard it both ways on plastic under concrete, I guess I am going to X-periment. The contractor is going to pour in 2 events, 20' x 60', then come back for the other 20' x 60' He asked if I wanted the plastic, he does not see the need. I told him to do 1 pour with plastic and 1 without. What can I expect in a cold shop, then using some type of heat. Will I see a difference in sweating between the 2 pours? Thanks , Brian |