Posted 2/28/2009 23:17 (#627046 - in reply to #626008) Subject: Re: Bin Drying Floor - Cement Block?
MS Delta
We have replaced floors in a couple of 20,000 bu bins. We were told by two different bin companies to place the blocks 1 ft a part each other. The blocks were placed up right with 1"x4" boards on top of the blocks. So far so good.