| We have a 2630 that I would like to tidy the data up on. I pulled the data off the head and put it in operations center. Then in operations center I merged some fields and cleaned up some guidance lines. I then created a setup file and loaded that back onto the 2630. I then realized that all my various offsets and implements were no longer available. Fortunately I had a copy of the old data and was able to revert it back. Is there a method I can use to update the data I want on the head but not interfere with all the implements and their offsets. When I pulled the data from the 2630 into operations center none of the implements I created on the head are shown so I can't add those back to the setup file. The only ones listed when I create the setup file are the ones created in operations center directly. We have a number of implements with offset data associated with them and I'd really like to avoid recreating all that from scratch sitting in the tractor. | |
|