Last week was a blast furnace, progress was made but it was a bit slower to ensure safety of the crew.
Finished Setting Rafters. Put steel on the roof. Formed out the window openings. Installed OSB, housewrap, and siding. Finished the soffit and trim on the roof less the peak cap. Windows installed. Most interior braces removed so we are ready to start forming the floor for concrete. Steel for the walls will be measured and ordered this week. Most of the ledge at the top of the wainscoat has been installed.