New Castle, PA | Not any help on your problems , sorry it did not work out for you. That is one of the issues with these regional or national pole building outfits , way to many sub contractors that they do not take the time to verify the work . After the main contractor gets paid , he is for the most part AOL. When you have a problem , the plumbers blame the electrician , the electrician blames the carpenters , the carpenters blame the excavator , the excavator blames the mason , etc. ,etc. Nothing but a damn circus and nobody cares after you got relieved of your $$$. In the last 10 years we have built a new house , and 3 sheds ,48X120 , 66X120 and 66X104 same contractor for all with his own dedicated crew . They done everything from start to finish. They were not the cheapest , but when a problem comes up I know who to talk to and they remedy the issue no questions ask | |
|