| February 2024 Sukup Bin Quote... Was cheapest per bushel between Golden Grain, GSI, Brock, and another Sukup dealer.
BIN
1. 36' 7 ring narrow corrugation 24,813 bu- $20,746.26
2. Inside ladder- $215.17
3. Outer stair with rail- $3,303.00
4. Floor- $8,088.76
5. 8 inch horizontal auger with power sweep and 7.5 hp motor- 4,542.12
6. Centrifugal fan with transition and 10 hp motor- $3,699.10
7. Gravity spreader for 13" auger- $1,250.00
8. 7 18" Roof Vents- $1,075.40
9. 24 Anchor Bolts- $358.21
10. Erection- $9,050.00
11. Freight- $1,200.00
Bin Total- $53,528.02
CONCRETE
1. Concrete Labor- $4,900.00
2. 60 yards of concrete- $8,700.00
3. 2000 feet of 1/2" rebar- $800.00
4. Gravel- $500.00
Concrete Total- $14,900
Grand Total- $68,428 or $2.86/bu
THIS DOES NOT INCLUDE ELECTRICAL WORK
| |
|