New Shed Project 5/12 - 8/6 Update
View previous thread :: View next thread
   Forums List -> Machinery TalkMessage format
 
mhiler100
Posted 8/6/2023 13:04 (#10346991)
Subject: New Shed Project 5/12 - 8/6 Update



NW IA
Here is the link to the previous threads:
https://newagtalk.com/forums/thread-view.asp?tid=1122982&posts=6#M10...

This week was wall week. Walls being built on the ground and then stood up in sections. Standard bracing during the week, then additional measures to shore up the walls with the potential for weather this weekend. A little wind so far, but mostly a very nice 1" rain last night and a steady rain/drizzle for a couple of hours today now, amount unknown as it is still going and haven't rechecked the gage yet.

Also, roof trusses were delivered, along with the I-beam for the overhead door in the side of the building that will support roof trusses. Hauled 3" clean rock and leveled to begin building the base for the driveway from the road to the building. Will pack and settle the new rock for awhile. Then will add 1" clean to come up to final grade and make a smoother path later. Initial goal of not ponding water on the driveway is a success so far.



(7-31 First Walls Built (full).jpg)



(7-31 First Walls Built 2 (full).jpg)



(7-31 Lumber Grade (full).jpg)



(8-1 First Walls Up (full).jpg)



(8-1 First Walls Up 2 (full).jpg)



(8-3 Door Header I-beam (full).jpg)



(8-3 Driveway Rock and Walls (full).jpg)



(8-3 Wall Bracing (full).jpg)



(8-3 Walls Up (full).jpg)



(8-4 Placing Wall (full).jpg)



(8-4 Placing Wall 2 (full).jpg)



(8-5 Braced for the storms (full).jpg)



(8-5 Braced for the storms 2 (full).jpg)



Attachments
----------------
Attachments 7-31 First Walls Built (full).jpg (103KB - 638 downloads)
Attachments 7-31 First Walls Built 2 (full).jpg (80KB - 585 downloads)
Attachments 7-31 Lumber Grade (full).jpg (50KB - 604 downloads)
Attachments 8-1 First Walls Up (full).jpg (75KB - 625 downloads)
Attachments 8-1 First Walls Up 2 (full).jpg (43KB - 607 downloads)
Attachments 8-3 Door Header I-beam (full).jpg (89KB - 577 downloads)
Attachments 8-3 Driveway Rock and Walls (full).jpg (78KB - 591 downloads)
Attachments 8-3 Wall Bracing (full).jpg (91KB - 576 downloads)
Attachments 8-3 Walls Up (full).jpg (80KB - 581 downloads)
Attachments 8-4 Placing Wall (full).jpg (70KB - 599 downloads)
Attachments 8-4 Placing Wall 2 (full).jpg (93KB - 628 downloads)
Attachments 8-5 Braced for the storms (full).jpg (79KB - 606 downloads)
Attachments 8-5 Braced for the storms 2 (full).jpg (40KB - 595 downloads)