NE SD | That's exactly how we poured new concrete under 4 of our 8500 bushel bins. We just went through the lid with the hook and then ran three cables bolted to the sides of the bins about 5' off the ground. Worked very well for us as all we had to do was swing them around with the handler. We tied them to the handler and they were only off the concrete for 4 days two at a time. Probably wasn't the best thing to do as now we have 30 year old aging bins with new concrete under them that will probably be useless in 15-20 years but we couldn't throw them away. | |
|